Purpose (problem description)

This page helps you to handle the following error : Another synchronization in the same measure is currently in progress this synchronization will wait and retry

Observed in CAST Version


Cast AIP Version

Yes

8.3.x
(tick)
8.2.x(tick)
Observed in RDBMS

RDBMS

Yes

Oracle Server(tick)
Microsoft SQL Server(tick)
CSS3(tick)
CSS2(tick)
Step by Step Scenario
  1. Check consolidate button
  2. Run application
Action Plan
  1. Check if there is a lock created for synchronization then removed it - SQL Queries - CAST Measure Base - Consolidation - Check if there is a lock created for synchronization and remove it

    1. Note that, starting from 8.3.7, the feature of removing the lock was added to the component - Remove lock

  2. If there is no lock on the measure schema, contact CAST Technical Support. with the following Relevant input

 