ENL - Updating Library Information following re-analyis

Updating Library information


If you have created Libraries and then re-run existing jobs that may update the objects in these Libraries or potentially add new objects to a parent object in these Libraries, then the following information will be of use:

Addition/Removal of an object into a parent structure
  • If the re-run of the job causes a new object to be added to the Knowledge Base and the new object's parent object is associated with a Library or Libraries, the new object will be automatically added to the same Library or Libraries.
  • If the re-run of the job causes an object to be dropped from the Knowledge Base, the object will also be automatically dropped from the Libraries to which it is associated.
Link updates

The update of Library links (i.e. links from or to Libraries) is not carried out automatically following the re-run of a job. You will need to manually run the Update Library Links option in CAST Analysis Manager or create an Update Library Links job that can be run on completion of other jobs to do so (see the on-line Help for CAST Analysis Manager for more information).

In the same way, if you delete (drop a Library) that contains objects that have links to another library (i.e. to other objects within the library), there is a risk that the links will be lost. CAST therefore highly recommends that you carry out an Update Library Links operation (see the on-line Help for CAST Analysis Manager) after you have created or modified a view containing Libraries.

See Also

Creating Libraries | Using Libraries